Project Description
59th Avenue Complete Streets Project includes constructing pedestrian improvements and landscaping along the east side of 59th Avenue NE, starting at the north parking lot of the Boys and Girls Club moving north approximately 450 feet north past 188th Street NE to incorporate Evans Park border. The scope also includes pedestrian improvements and street trees from 59th Avenue east on 188th Street NE, along the southern gravel parking lot. Three gravel parking lots will obtain drainage, paving, and striping: Evans Park (both parking lots) and Quake Park (north parking lot). Solar powered flashing LED pedestrian crosswalk signs will be installed connecting the Boys and Girls Club to the Airport Trail and connecting the north and south parking lots on 188th Street.
Project Benefits
- Improve corridor safety
- Improve pedestrian safety
- Increase parking
Project Cost and Funding
- Engineer’s estimate: $1,100,000
- Funding by:
- Transportation Improvement Board $600,000
- Department of Commerce $519,400
Project Schedule
- Final Design: June, 2021
- Construction start: October, 2021
- Estimated Completion:
Questions?
If you have questions or concerns on this project, please contact the Community and Economic Development Department 360-403-3551 ced@arlingtonwa.gov